CITB test is a test which is used to assess the occupational competency of individuals working in the construction site. It is a multiplechoice question & answer exam. The questions cover topics such as safety, health and environment, construction site procedures and materials. Passing the CITB test is a must requirement for CSCS Card.  Start practicing for your CITB Test today!

Before planning for anyone to enter a confined space, following the principles of prevention, what should be the first consideration of the manager or supervisor?

 
 
 
 

The advantage of using safety nets rather than harness and lanyard is that:

 
 
 
 

What is the purpose of the health and safety file on a construction project?

 
 
 
 

When is it advisable to take precautions to prevent the fall of persons, plant or materials into an excavation?

 
 
 
 

What is the MAIN danger of leaving someone who has fallen suspended in a harness for too long?

 
 
 
 

If your company is the principal contractor on a project that is notifiable under the current Construction (Design and Management) Regulations, you may come into contact with the CDM co-ordinator because of their legal duty to:

 
 
 
 

You will find the details of the welfare facilities that must be provided on site in which regulations?

 
 
 
 

On a scaffold the minimum height of the main guard-rail must be:

 
 
 
 

In the colour coding of electrical power supplies on site, what voltage does a blue plug represent?

 
 
 
 

When putting people to work above public areas, your first consideration should be to:

 
 
 
 

Which piece of equipment is used with a cable avoidance tool (CAT) to detect cables?

 
 
 
 

What danger is created by excessive oxygen in a confined space?

 
 
 
 

Under the current Construction (Design and Management) Regulations, which of the following must the principal contractor ensure is specifically provided before allowing any demolition work to commence?

 
 
 
 

For a ladder, what is the maximum vertical height that may be climbed before an intermediate landing place is required?

 
 
 
 

If a scaffold is not complete, which of the following actions should be taken by the site manager?

 
 
 
 

How should cylinders containing liquefied petroleum gas (LPG) be stored on site?

 
 
 
 

In deciding what control measures to take, following a risk assessment that has revealed a risk, what measure should you always consider first?

 
 
 
 

In considering what measures to take to protect people against risks to their health and safety, personal protective equipment (PPE) should always be regarded as:

 
 
 
 

On a scaffold the unprotected gap between any guard-rail, toe-board, barrier or other similar means of protection should NOT exceed:

 
 
 
 

How should access be controlled, if people are working in a riser shaft?

 
 
 
 

Question 1 of 20

Don’t get confused! Just Fill your details & get quick support for your CSCS Card.

Get on site with right CSCS Card!

Fill in a few details to get started with the application. The process is simple and takes only a few minutes.